You do not need scheduling software to judge a schedule update. You need eight questions and the discipline to ask them every month. Together they tell you whether the finish date moved, why, and whether the forecast in front of you can be trusted.
This guide is written for owners, developers and project managers who receive a monthly update and want to know what to look for before they accept it.
Key points
- Start with the finish date: did it move, and does the narrative say why?
- The critical path should be explainable in one sentence. If it changed, ask what changed it.
- Compare reported progress with the pay application and with what you see on site.
- A finish date that never moves while activities slip is a warning, not good news.
The eight questions
1. Did the completion date move?
Compare the projected substantial completion date with the contract date and with last month’s update. Do the same for every contract milestone. A change in either direction needs an explanation in the narrative.
2. What is the critical path — and is it the same as last month?
Ask for a layout showing only the path that drives each contract milestone. For final completion that is the longest path; for substantial completion or an interim milestone it can be a different one (why the two can differ). You should be able to read it as a sentence: “dry-in, then interior finishes, then inspections.” If the path jumped to different work since last month, something significant happened, and the narrative should name it.
3. How much float does the near-critical work have?
Work with only a few days of float is next month’s critical path. Track the float on the main paths from update to update. Float that shrinks every month is slippage that hasn’t reached the finish date yet.
4. Does reported progress match reality?
Check percent complete against the pay application and against what is physically in place. A schedule showing framing 80% complete while the pay application bills 55% deserves a conversation.
5. What changed besides progress?
Updates should record progress. Changes to logic, durations, calendars or the activity list are revisions, and each should be listed with a reason. Ask for a change log, or have the file compared with last month’s.
6. Is next month’s work actually ready?
Look at what is due to start before the next update. Are the submittals approved, the materials on site or on order, the area available? Planned starts that keep sliding are an early sign of trouble.
7. What delays are being recorded?
Has the contractor given notice of any delay? Is a time impact analysis attached or promised? Events that appear in the schedule without notice — and notices with nothing in the schedule — both need follow-up.
8. Is the remaining plan realistic?
Compare remaining durations with performance so far. If framing has averaged four weeks a floor, a plan to finish the last two floors in three weeks needs an explanation: more crew, a different method, or optimism.
Red flags worth a closer look
- The finish date never moves even though individual activities are finishing late. Either float is being used up or the remaining plan is being compressed.
- Remaining durations on critical work get shorter with no explanation.
- Out-of-sequence progress: work reported complete before its predecessors. The logic no longer reflects how the job is being built.
- Actual dates after the data date, or remaining work still forecast before it. The update wasn’t statused properly.
- New constraints holding milestones in place.
- A PDF with no native file. Logic and float cannot be checked from a picture.
- A narrative that doesn’t mention any of the above.
What to ask for with every update
- The native schedule file, not only a PDF
- A narrative explaining progress, changes and the critical path
- A critical path layout
- A milestone table: baseline, last update, current forecast
- A list of every change to logic, durations and calendars
If your contract doesn’t require these, ask anyway. A contractor with a sound schedule can produce all five without difficulty.
When to bring in a scheduler
The eight questions will catch most problems. An independent review goes further: opening the native file, testing the logic, comparing it line by line with the previous submission, and telling you how much confidence the forecast deserves. It is worth considering when the finish date starts to move, when a time-extension request arrives, or when a lender or board needs more than the contractor’s word. Our guide on when to hire a scheduling consultant lists what to ask.