Retained logic and progress override are two settings in Primavera P6 that decide what happens to remaining work when an activity starts out of sequence — before its predecessors are finished. Retained logic makes the remaining work wait for those predecessors. Progress override lets it carry on as if the broken link were not there.
The choice matters more than it sounds. The same schedule, with the same progress, can show completion dates days or weeks apart depending on which option is selected.
Key points
- Out-of-sequence progress means work started before the logic said it could.
- Retained logic is conservative and is P6’s default. Progress override is optimistic.
- Many owner specifications require retained logic.
- The setting treats the symptom. Correcting the logic treats the cause.
What out-of-sequence progress is
A schedule says drywall on level 3 cannot start until the in-wall inspection is finished. On site, the drywall crew starts in the east wing while the inspector is still working through the west. When the schedule is updated, drywall has an actual start and the inspection is not complete. That is out-of-sequence progress.
It is not a mistake by the field. Usually it means the schedule’s logic was stricter, or coarser, than the way the work is really built. But the software now has to decide what to do with the drywall that remains.
The three options in P6
In P6’s schedule options, under “When scheduling progressed activities use,” there are three choices:
| Option | What it does | Effect |
|---|---|---|
| Retained logic | The remaining duration of the out-of-sequence activity waits until its predecessors finish. | Later, more cautious dates. Can leave a gap in the middle of an activity. |
| Progress override | The relationship is ignored. Remaining work continues from the data date. | Earlier dates. The predecessor may be left driving nothing. |
| Actual dates | Calculates from the actual dates recorded, even where they fall out of order. | Rarely specified. |
Retained logic is the default in P6.
A worked example
At the data date, the in-wall inspection has 5 working days left. Drywall, its successor, has already started and has 8 days of work remaining.
- Retained logic: the remaining 8 days of drywall wait for the inspection. Drywall finishes 13 working days after the data date.
- Progress override: the remaining 8 days start now. Drywall finishes 8 working days after the data date, and the inspection no longer holds anything up.
Five days’ difference from one setting. If drywall is on the critical path, the projected completion date moves by the same five days.
Which answer is true? Neither, quite. Retained logic assumes no more drywall can be hung until every inspection is done. Progress override assumes the inspection doesn’t matter at all. The real job sits somewhere between the two.
What specifications require
Many owner specifications, federal ones among them, require retained logic. It is the cautious choice: it cannot make a schedule look better than its logic allows. Check the scheduling specification before the baseline is built, and state the setting in the schedule narrative.
Whatever the contract says, the setting should not change partway through a job without agreement. Switching from retained logic to progress override can pull a late completion date back onto the contract date without any work being done differently. Reviewers compare settings between updates for exactly that reason.
The better answer: fix the logic
Out-of-sequence progress is the schedule telling you its logic is wrong. The durable fix is to make the logic match the work:
- Find the activities. P6’s schedule log lists every activity with out-of-sequence progress each time the schedule is calculated.
- Ask why. Was the link too rigid, or is the activity too big? “Level 3 drywall” following “Level 3 inspection” breaks the moment the work is done wing by wing.
- Correct it. Split the activities by area, or replace the finish-to-start link with a start-to-start link and a finish-to-finish link, so the inspection’s finish still holds the end of the drywall.
- Record it. List the logic change and the reason in the narrative.
A schedule with few out-of-sequence activities gives nearly the same answer under either setting. That is the sign of healthy logic, and it is what we aim for in every update.
The equivalent in Microsoft Project
Microsoft Project has one switch for the same question: “Split in-progress tasks,” in the schedule options. With it on, remaining work on a task that started early is pushed out to follow its predecessors, much like retained logic. With it off, remaining work continues from where it stands, much like progress override.
The same advice applies. Know which way it is set, say so, and fix the links that keep tripping it. Our P6 and Microsoft Project comparison covers how the two programs differ.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.