Software

Critical Path vs. Longest Path in Primavera P6: Which to Use

How Primavera P6 marks critical activities by total float or by longest path, why the two lists differ, which to use, and how to check both.

Primavera P6 can mark critical activities in two ways. By total float, it marks every activity whose float is at or below a number you set, usually zero. By longest path, it marks the chain of driving activities that leads to the last activity in the schedule, whatever float those activities show.

On a simple schedule the two lists usually match. Add a second calendar, a date constraint or a finish date that is being missed, and the same file can give two different lists. Which one you are reading depends on one setting.

Key points

  • P6 marks critical activities by total float or by longest path, and one setting decides which.
  • The longest path follows driving relationships back from the last activity and ignores float values.
  • Calendars, date constraints and a missed finish date make the two lists differ.
  • Follow the specification, name the definition in the narrative, and don’t switch without explaining why.

Where the setting is in P6

In P6 Professional, choose Tools, Schedule, then click Options. On the General tab of the Schedule Options dialog box, “Define critical activities as” has two choices:

Choice in P6What it marks criticalWhere it can mislead
Total Float less than or equal toEvery activity with total float at or below the threshold you enter.Several calendars, date constraints, or a missed finish date.
Longest PathEvery activity on the chain that drives the last activity in the schedule, whatever its float.The last activity is not the milestone that matters, or the chain starts at a constrained date.

The same two choices appear on the Settings tab of Project Details, under “Critical Activities.” P6 applies the choice when the schedule is calculated. It changes which activities are marked critical. Dates and float values stay the same.

What each test marks

Total float

P6 marks every activity whose total float is at or below the threshold. At zero, that is the rule in our plain-English guide to CPM: no float, so critical. Negative float is marked too.

The threshold is not always zero. A specification may set a number of days, or a team may raise it to bring near-critical work into the list. Type the unit with the number: P6 reads a bare “5” as five hours, not five days.

The test reads one number per activity. It does not ask where the activity leads.

Longest path

Here P6 does not read float. It finds the activity or activities with the latest early finish, then traces every driving relationship back from there. A relationship is driving when the predecessor sets the successor’s early dates. Every activity on that trace is marked critical, whatever its float.

Why the two disagree

With one calendar, no date constraints and no required finish date, the two tests usually mark the same activities. Three things pull them apart.

A date constraint off the longest path

A parking level must be turned over early, so its turnover milestone carries a “Finish On or Before” constraint, which limits late dates only. The work leading to it is forecast to finish 6 working days after the constraint date, so every activity on the chain driving the milestone shows 6 days of negative float. The float test marks them all. It would mark them even if the milestone were forecast exactly on its date, at zero float. The longest path marks none: the tower above drives the last activity in the schedule.

Calendars that change along one chain

Take three activities on the driving chain. A deck pour on a five-day calendar finishes on a Friday. Curing, on a seven-day calendar, takes 7 days and ends the next Friday. Form stripping, back on the five-day calendar, starts Monday. The cure could run through the weekend without delaying the stripping, so it shows 2 days of float. The pour and the stripping show none. A zero-float filter shows a critical path with a gap in it. The longest path marks all three.

A required finish date that is being missed

The project has a “Must Finish By” date equal to the contract completion date, and the update forecasts completion 15 working days later. P6 works late dates back from the earlier date. Every activity that would otherwise have 15 days of float or less now shows zero or negative float, and the float test marks it critical. That can be most of the remaining work. The longest path is still the one driving chain. A “Finish On or Before” constraint on the completion milestone does the same.

The reverse also happens. When the forecast beats the “Must Finish By” date, every activity shows positive float and a zero threshold marks nothing.

Out-of-sequence progress: a different setting

Out-of-sequence progress can change the critical activities too, through another setting. Drywall on the driving chain has started while the in-wall inspection before it has 5 days left. Under retained logic, the remaining drywall waits those 5 days, so the inspection has no float. Under progress override, P6 ignores the link and the inspection holds nothing up. Our guide to retained logic and progress override works through the dates. Check for out-of-sequence work near the path before trusting either list.

Which one to use

  1. Start with the scheduling specification. Some define the critical path as the longest path. Others define critical work by a float value. If yours says, that settles it.
  2. If it is silent, use the longest path where float is distorted: several calendars, constrained interim milestones or a “Must Finish By” date. Oracle’s own help says float can mislead on a schedule with several calendars. Keep reporting float too: it shows how far each activity is from the dates it must meet.
  3. State the definition in the narrative. One sentence in the schedule narrative is enough.
  4. Don’t switch between updates without explaining why. A new definition can add or remove critical activities when nothing on site has changed.

How to see both in P6

You can compare the two without changing the setting.

  • Columns. Choose View, Columns and add Critical, Longest Path and Total Float. Critical follows whichever definition is selected. Longest Path marks the activities on the trace.
  • Filters. P6’s predefined activity filters include one named Critical and one named Longest Path.
  • Float paths. On the Advanced tab of Schedule Options, “Calculate multiple float paths” ranks the chains leading to an activity you choose and stores the rank in the Float Path column. Use it for a milestone that is not the last activity.

Activities marked in one column and not the other should each have a cause you can name.

A note on Microsoft Project

Microsoft Project uses a slack test. A task is critical when its total slack is at or below the value in “Tasks are critical if slack is less than or equal to,” under File, Options, Advanced. The default is 0 days. Constraints and deadline dates affect slack, so they affect the list too.

The same page has a “Calculate multiple critical paths” checkbox. By default Project shows one critical path, the one that affects the project’s finish date. With the box selected, each independent network of tasks is treated as its own project for late dates, so each gets a critical path. Our P6 and Microsoft Project comparison covers the other differences.

Common mistakes

  • Reading a zero-float filter as the critical path on a schedule with several calendars. Expect gaps.
  • Calling every negative-float activity critical. With a “Must Finish By” date, that list shows what is late against that date, not what is driving the finish.
  • Assuming the longest path ends at substantial completion. It ends at the last activity in the schedule. If closeout runs later, the path leads there.
  • Accepting a longest path that starts at a constraint without checking the constraint. The trace stops where no predecessor is driving, as at an activity held by a “Start On or After” date.
  • Assuming every schedule uses the same definition. Check the setting in each file you receive.

This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.

Quick answers

Questions, answered.

Is the longest path the same as the critical path?

Often, but not always. With one calendar and no date constraints, the longest path and the zero-float activities usually match. With several calendars, date constraints or a missed finish date they can differ, and the specification should say which one it means.

Can an activity on the longest path have float?

Yes. The longest path comes from tracing driving relationships, not from float values. A cure activity on a seven-day calendar between two activities on a five-day calendar is a common case.

Why does my P6 schedule show so many critical activities?

Usually negative float. If critical is defined by total float and the forecast finish is later than a “Must Finish By” date or a constrained milestone, every activity without enough float to absorb the slip is marked critical. The Longest Path column shows which chain is driving the finish.