A schedule narrative is the written report that accompanies a schedule submission. It explains in words what the schedule shows: the plan and its assumptions at baseline and, at each update, what progressed, what changed, what is critical and what is at risk.
Most CPM specifications require one, and it is usually the only part of the submission most people read. A good narrative is short, specific, and impossible to write without understanding the schedule — which is exactly why owners ask for it.
Key points
- The narrative explains the schedule; it should never simply restate the bar chart.
- A baseline narrative documents assumptions. An update narrative documents change.
- Every movement in the completion date needs a cause, in writing, in the month it happens.
- End with decisions: what you need, from whom, and by when.
What goes in a baseline schedule narrative
The baseline narrative — often called the basis of schedule — records how the plan was put together, so that a reviewer can test it and so that anyone can later see what was assumed.
- Scope and basis. The contract documents, drawings and addenda the schedule was built from.
- Structure. The work breakdown structure and the activity codes for area, phase, trade and responsibility.
- Calendars and weather. Work weeks, holidays, and how anticipated weather days were included.
- Durations. The crews, equipment and production rates behind the major durations.
- Sequence and phasing. The construction approach, access restrictions and turnover order.
- Critical path. A plain description of the longest path from start to completion, and the near-critical paths behind it.
- Milestones and constraints. Each contract date and each constraint used, with the reason for it.
- Procurement. Long-lead items, their lead times and when they must be released.
- Owner activities. Review periods, owner-furnished items and third-party work the schedule depends on.
- Software settings. The calculation settings that affect dates, such as how out-of-sequence progress is handled.
Some owners spell this out. The Idaho Transportation Department’s standard specification, for example, requires a narrative with the CPM schedule describing the major equipment and assumed production rates for the major work activities.
What goes in a monthly update narrative
An update narrative answers one question: what is different from last month, and why?
- Summary. The data date, the projected completion date and its variance from the contract date and from the last update.
- Progress this period. What started, what finished, and what fell short of the plan.
- Changes to the schedule. Any added or deleted activities and any change to logic, durations or calendars — each with its reason.
- Critical path. The current critical path, and how it differs from the previous update.
- Milestones. Baseline, previous and current dates for each contract milestone.
- Delays and notices. Events affecting time, the notices given, and any time impact analysis submitted or to come.
- Decisions needed. What you need from the owner, the design team or others, and the date by which you need it.
- Next period. The main work planned before the next data date.
An example update narrative
The example below is illustrative. It describes a five-story mixed-use building in its eighth month, in the week a long-lead delivery slips.
Schedule Update 08 — data date: November 1, 2026
1. Summary. Projected substantial completion is June 4, 2027. This is 21 calendar days later than the contract date of May 14, 2027 and 21 calendar days later than Update 07, which showed the project on time.
2. Progress this period. Wood framing topped out on level 5. Roofing began on the east half and is 43% complete. MEP rough-in is 44% complete, in line with the plan.
3. Changes this period. The switchgear manufacturer revised its ship date from December 11, 2026 to February 19, 2027 (manufacturer’s letter attached). The remaining duration of “Switchgear — fabricate and deliver” was increased to match. No logic was changed and no activities were added or deleted.
4. Critical path. Switchgear delivery → set and terminate gear → permanent power → elevator inspection → commissioning → final inspections → substantial completion. Last period’s critical path, through interior finishes, now has three weeks of float against the projected completion date and none against the contract date.
5. Delays and notices. Written notice of the switchgear delay was given on receipt of the manufacturer’s letter. A recovery plan is under review and will be submitted with Update 09.
6. Decisions needed. (a) Authorization to energize equipment on temporary power for start-up, needed by November 13, 2026. (b) Confirmation that phased turnover by floor is acceptable.
7. Next period. Complete roofing on the east half; start window installation on level 2; continue rough-in on levels 3 to 5.
Notice what it does in under 250 words. It states the result first, gives one cause for the change, says plainly that nothing else was altered, and ends by asking for two decisions with a date attached.
An outline you can reuse
- Project, update number and data date
- Summary: projected completion and variance
- Progress this period
- Changes to logic, durations, calendars and activities — with reasons
- Critical and near-critical paths
- Milestone status table
- Delays, notices and time impact analyses
- Decisions and information needed, with need-by dates
- Work planned for next period
- Attachments: layouts, change log, supporting documents
Keep the same headings every month. Readers learn where to look, and a section that suddenly says something different stands out.
Our free schedule narrative template sets this outline out as a Word document, with an instruction under each heading and the example above to write over.
Free download
Schedule narrative template
The ten headings above, an instruction under each and a worked example to write over.
Mistakes that get narratives rejected
- Describing the bars. “Framing continues on level 3” adds nothing the layout doesn’t already show.
- Unexplained movement. A completion date that changed with no stated cause.
- Silent edits. Logic or durations changed without being listed. Reviewers compare files, and they will find them.
- No critical path. If the narrative can’t describe what is driving completion, the schedule probably can’t either.
- Boilerplate. The same paragraphs every month, with only the dates changed.
- Good news only. A narrative that never mentions a problem stops being believed.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.