A three-week look-ahead is a short-interval schedule showing the work each crew will perform, day by day, over the next three weeks. It is built from the CPM schedule but written at the level of detail a foreman plans at, and it is updated every week.
It is the most-used schedule on any job site — and on many projects it has quietly stopped matching the contract schedule. This guide covers how to build one that stays tied to the CPM and earns its place at the weekly meeting.
Key points
- A look-ahead breaks CPM activities into daily tasks by area and trade.
- Tie every task to a CPM activity ID so weekly progress feeds the monthly update.
- Screening constraints is the point: a task isn’t ready until what it needs is in place.
- Review last week before planning next week. The misses tell you what to fix.
What a good look-ahead contains
- Tasks by area and trade — “Level 3 east: hang drywall,” not “Level 3 finishes.”
- Daily bars across fifteen working days.
- The CPM activity ID each task belongs to.
- What each task needs first: an RFI answer, an approved submittal, a delivery, an inspection, access, or the trade ahead.
- Who is responsible for the task and for clearing each constraint.
- Critical work flagged, so everyone knows which tasks cannot slip.
The window itself varies by owner. Some define it as three weeks ahead. Others want one week back and two ahead: the City of Los Angeles Bureau of Engineering, for example, asks for a weekly three-week progress schedule listing the previous week’s activities and those planned for the next two.
How to build it, in seven steps
- Start from the current CPM update. Filter for activities in progress or starting in the next three weeks.
- Break the activities down. A 20-day rough-in activity becomes tasks by area and crew, a few days each.
- Ask the people doing the work. Foremen set the durations and the order. A look-ahead they didn’t help make is one they won’t follow.
- Screen every task for constraints. Design information, materials, labor, equipment, inspections, access, preceding work, weather.
- Publish it before the meeting, so the trades arrive having read it.
- Review last week. What was planned, what was done, and why the difference.
- Feed the actual dates back into the CPM schedule for the next update.
A free three-week look-ahead template
If you would rather start from a working file than a blank sheet, this is the format described above as an Excel workbook. It is free, and there is no form to fill out.
Free download
Three-week look-ahead template
Type a start date and a number of working days for each task, and the bar draws itself.
- Fifteen weekday columns that date themselves from the Monday you enter.
- Bars that draw themselves from each task’s start date and working days, skipping weekends and the holidays you list.
- Critical-path work in a second color, so the tasks that cannot slip stand out.
- A constraint log on every row: what the task needs first, who is clearing it, and the date it is needed by.
- A column for the CPM activity ID, so weekly progress can be carried into the monthly update.
The file opens with a worked example to type over: the Level 3 and roof sequence shown on our look-ahead schedules page. A second sheet explains each column and holds the holiday list. It is set up to print on 11 × 17 paper, landscape, one page wide. The template page walks through each column and the eight steps for using it.
Pulling a look-ahead from Primavera P6
P6 can produce the starting list in a saved layout:
- Create a filter for activities that are not complete, start on or before the data date plus three weeks, and finish on or after the data date. P6 accepts rolling dates in filters, such as the data date plus three weeks, so the layout updates itself each period.
- Group by area or trade, and sort by start date.
- Set the timescale to days and weeks, and show the activity ID, remaining duration and total float.
- Save the layout and export it as a PDF.
That gives you the CPM activities in the window. The daily task breakdown usually lives in a companion sheet, keyed to the activity IDs, because adding foreman-level detail to the contract schedule makes it harder to maintain and to review.
Pulling a look-ahead from Microsoft Project
- Set the status date to the end of the week.
- Apply the built-in Date Range filter, or a custom filter for tasks that are under 100% complete, start before the end of the window, and finish after the status date.
- Group by a custom field for area or trade.
- Zoom the timescale to days, and print or save as PDF.
Hide summary tasks in the filtered view, or the list fills with headings instead of work.
Running the weekly meeting from it
A look-ahead is only as good as the meeting that uses it. A workable agenda takes thirty minutes:
- Last week: each trade says what it finished and what it didn’t, and why.
- Next week: walk the tasks area by area. Each foreman confirms or changes the dates.
- Constraints: go down the list. Who is clearing each one, and by when?
- Weeks two and three: what has to be ordered, inspected or answered now so the work is ready then.
- Critical path: the two or three tasks that must not slip this week.
The measure of the meeting is the commitments people leave with. If the reasons for last week’s misses repeat — the same late delivery, the same unanswered RFI — the look-ahead has shown you where the job is really losing time.
Common mistakes
- A look-ahead divorced from the CPM. Two plans, one for the field and one for the owner, that drift apart until the update is fiction.
- Too coarse. The same activity names as the master schedule, with the bars cut off at three weeks.
- No constraints column. Dates without the conditions they depend on.
- Written by one person. The superintendent’s view only, with no commitment from the trades.
- Never looking back. Planning next week without asking why last week’s plan wasn’t met.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.