Change & delay

Construction Delay Analysis Methods Compared: How to Choose One

The main construction delay analysis methods compared: how each works, the schedules and records it needs, where it is weak, and how to choose between them.

In this guide

The main methods of construction delay analysis are as-planned versus as-built, impacted as-planned, time impact analysis, windows analysis (also called contemporaneous period analysis) and collapsed as-built, or but-for, analysis. Each measures the effect of delay events on a project’s completion date. They differ in the schedules and records they need, and in whether they look forward or back.

No method is right for every job. The contract may name one, and the surviving records decide what can be done reliably. This guide explains how each works, what it needs and where it is weak.

Key points

  • Prospective analysis forecasts a delay during the job, and retrospective (forensic) analysis explains it afterward.
  • No method is best in every case: the contract and the records narrow the choice.
  • Whatever the method, the result is only as good as the baseline, updates and records behind it.
  • In a dispute, the contract and the forum govern, and the method should be chosen with counsel.

Prospective or retrospective: forward or back?

Prospective analysis is done during the job, as an event arises. It looks forward: from the current schedule, it forecasts what a change or delay is likely to do to the completion date, so time can be settled with the change order.

Retrospective analysis, often called forensic analysis, is done afterward, when the effects are known. It looks back through the schedules and the project record to establish which events delayed completion, and by how many days.

The two can give different answers. A forecast might show a late design change costing ten working days. A look back might find the crew resequenced the work and lost four. They answer different questions.

The five main methods

Publications name and group the methods differently. The Society of Construction Law Delay and Disruption Protocol, 2nd edition (2017), describes six methods. AACE International’s Recommended Practice 29R-03, Forensic Schedule Analysis, classifies methods as observational or modeled, and modeled methods as additive or subtractive. Put simply, an observational method studies the schedules as they are. A modeled method adds delay events to a schedule, or removes them, and measures the result.

As-planned versus as-built

The baseline plan is set beside what actually happened, activity by activity. Late starts and longer durations are traced to their causes along the path that controlled completion. It needs a reliable baseline and good as-built dates, taken from updates or rebuilt from daily reports. It is observational and easy to explain. Its weakness: it shows that work was late more readily than why, and it struggles when the critical path shifted during the job.

Impacted as-planned

Delay events are added to the baseline schedule, which is recalculated. The movement in the completion date is taken as the delay. It is modeled and additive, and it asks the least of the record: a sound baseline and the facts of each event. Its weakness is that it ignores what happened on site. Actual progress, changes in sequence and delays left out of the model play no part.

Time impact analysis

A fragnet, a small network of activities representing the event, is inserted into the schedule update that was current when the event arose. Completion is compared before and after. It is additive too, but starts from the job’s actual status, not the original plan. It needs reliable updates and a documented fragnet. AACE International’s Recommended Practice 52R-06 describes the method, and our time impact analysis guide works through an example. Its weakness: it measures the expected effect of an event, which may not be what actually happened.

Windows analysis

Also called contemporaneous period analysis. The job is divided into periods, usually the intervals between schedule updates. For each, the analysis measures how the projected completion date and the critical path moved from one update to the next, then uses the project record to explain why. It is observational. It needs a baseline and regular, reliable updates. Its weakness is that dependence: where updates are missing, careless or revised without explanation, the analysis inherits the problem. The name is used loosely, so ask what was actually done.

Collapsed as-built

Also called but-for analysis. The analyst builds a schedule of the job as it was actually built, with logic ties between activities, then removes the delays under study, usually one party’s, and recalculates. The earlier finish shows when the work would have been complete but for those delays. It is modeled and subtractive. It needs detailed as-built records, though not a full set of updates. Its weakness is the as-built logic, which the analyst assigns after the fact. Different reasonable choices can give different answers.

The methods side by side

MethodLooksWhat it needsBest suited toMain weakness
As-planned vs. as-builtBack, against the baselineBaseline and as-built datesSimpler jobs with few updates but good as-built recordsShows what was late more readily than why
Impacted as-plannedForward, from the baselineBaseline and event detailsSimple cases early in a jobIgnores actual progress
Time impact analysisForward, from the update at the timeReliable updates and a documented fragnetSettling time as changes happen, or where the contract requires itMeasures the expected effect, not the actual one
Windows analysisBack, period by periodBaseline, reliable updates and project recordsA late finish where many events overlappedOnly as good as the updates
Collapsed as-builtBack, from the as-built scheduleAn as-built schedule with logic, built from detailed recordsDetailed as-built data but no reliable updatesAs-built logic rests on the analyst’s judgment

Treat the table as a map, not a rule.

How to choose a method

Five questions, in this order.

  1. What does the contract require? Many contracts name the method for a time-extension request, commonly a time impact analysis, and the form it must take. Start there.
  2. What records exist? An accepted baseline, a full set of updates and daily reports keep every option open. A baseline and little else closes most of them.
  3. Can the updates be trusted? Methods built on updates assume each one recorded progress accurately and explained its logic changes. If they fail the basic checks, the analysis has to lean on the as-built record.
  4. How much is at stake? Effort should be in proportion to the dispute. A period-by-period study of a two-year job is hard to justify for a week of disputed time.
  5. Where will it be decided? A negotiation, a mediation, an arbitration and a courtroom ask different things of an analysis. Each needs a result non-schedulers can follow.

None of this is legal advice. The contract and the forum govern, and in a dispute the choice of method should be made with counsel. Any delay analysis should start with what the evidence can support.

What every method depends on

The methods lean on different mixes of the same three things, and none makes up for what is missing.

  • A sound baseline. Complete scope, real logic and defensible durations. One that fails a basic review gives a critical path nobody can rely on.
  • Regular updates. Issued on time, with accurate actual dates and every logic change listed. They record what was critical at the time.
  • Contemporaneous records. Daily reports, meeting minutes, RFI and submittal logs, photos and correspondence. They tie each day of delay to a cause.

On a live job, the quality of any later analysis is decided now, one update at a time.

Concurrent delay and float

Concurrent delay is two or more independent delays that affect the critical path in the same period, each of which would have delayed completion on its own. Say the footings are critical. The owner’s revised foundation drawings arrive two weeks late and, for unrelated reasons, so does the contractor’s concrete crew. A model that inserts only one party’s events cannot show that, so the analysis has to cover what both parties were doing on the critical path. How concurrency is treated depends on the contract and the governing law.

Float absorbs delay before completion moves. A delay has to use up the float on its path first, so a sound analysis tests each delay against the critical path as it stood at the time. Who may use the float is set by the contract, as our guide to who owns the float explains.

Common mistakes

  • Choosing the method for its answer. It should follow the contract and the records, not the number it produces.
  • Counting days instead of testing criticality. Thirty days of late RFI answers is not thirty days of delay. Only delay to the critical path moves completion.
  • Modeling one side’s delays only. Leave out your own late work and the other side will put it back.
  • Trusting the schedules unchecked. Broken logic in a baseline or update passes into every result built on it.
  • Correcting schedules silently. Every correction should be listed and explained.
  • Leaving it to the end. Records thin out, people move on, and notice periods may already have passed.

This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.

Quick answers

Questions, answered.

Which delay analysis method is best?

None is best in every case. The contract may require one, and the schedules and records that exist limit what can be done reliably. Choose the one the contract allows and the evidence supports.

Can a delay analysis be done without schedule updates?

Usually, but the choice narrows. Methods that work from contemporaneous updates lose their footing, and the analysis leans harder on the baseline and the as-built record: daily reports, photos, inspection records and correspondence.

What is a but-for analysis?

Another name for the collapsed as-built method. The delays under study are removed from a schedule of the work as built, which is then recalculated to show when the job would have finished but for them.

Free 30-minute consultation

Bring your schedule, your spec or just your questions.

Thirty minutes with a scheduler, no obligation. We will look at where your project stands and tell you plainly what would help.

Call Free consultation