Float is the time an activity can slip before it delays completion. Who gets to use it — the owner, the contractor, or whoever needs it first — is decided by the contract. Most contracts that address the question say float belongs to the project, which means it is used on a first-come, first-served basis.
That one clause quietly decides a lot. Under it, a delay that only uses up float earns no time extension, however clearly someone else caused it.
Key points
- Float is calculated from the schedule’s logic. Nobody grants it and nobody owns it until the contract says so.
- Most contracts that address float treat it as a shared project resource: first come, first served.
- A delay has to use up the float on its path before it can move the completion date.
- Record who used the float and why, even when no time extension is due.
What float is — and isn’t
Total float is the amount of time an activity can be delayed without delaying project completion. Free float is the amount it can be delayed without delaying the activity that follows it. Both are results of the CPM calculation; neither is typed in.
Two points are easy to miss. Float belongs to a path, not to a single activity: ten activities in a chain share the same ten days, and when one of them uses four, the rest have six. And float is not contingency. Contingency is time someone deliberately sets aside. Float is simply what the logic leaves over.
Three ways contracts assign float
| Approach | What it means | How common |
|---|---|---|
| Project float | Float is a shared resource. Whoever needs it first uses it, and neither party is compensated for the float the other consumed. | By far the most common |
| Reserved float | The contract sets aside some or all of the float for one party, usually the owner. | Found in some public contracts |
| Silent contract | Nothing is said. Ownership is argued from the rest of the contract and the governing law. | Common on smaller private work |
Idaho’s public contracts show the first approach in two styles. The Division of Public Works contract puts it in one line: “Schedule float shall belong to the Project.” The Idaho Transportation Department’s specification spells it out, making float before substantial completion available to either party on a first-come, first-served basis and giving float after substantial completion to the contractor.
Always read your own contract. The wording varies, and it controls.
Why ownership matters
- Time extensions. Under a project-float clause, an owner-caused delay earns time only to the extent it pushes completion past the contract date. Delay absorbed by float earns nothing.
- Early-completion schedules. If the contractor plans to finish a month early, that month sits between its planned finish and the contract date. Many contracts treat it as float, available to both parties.
- Hidden float. Padding durations, adding lags or pinning activities with constraints can tuck float away where the other party can’t use it. Reviewers look for it, and finding it damages trust in the whole schedule.
- Slow decisions. Late approvals and unanswered questions often consume float invisibly. The schedule still shows the same finish date, with less room behind it.
First come, first served: a worked example
A path of work through the mechanical rooms has 10 working days of total float.
- The owner takes 6 days longer than the contract allows to return a submittal. The path’s float drops from 10 days to 4. Completion does not move, so no time extension is due.
- Two months later, a delivery the contractor is responsible for arrives 7 days late on the same path. The first 4 days use the remaining float. The last 3 push completion.
Under a project-float clause, the 3 days of critical delay belong to the contractor’s late delivery, even though the owner used more of the float. The owner simply got there first.
That can feel unfair to the contractor, and it is why the record matters. A schedule update that showed the float falling from 10 days to 4, with the cause written in the narrative, is the contractor’s evidence if the two events are later argued together.
What to do about it
If you are the contractor
- Read the float clause before the baseline is built.
- Give notice when someone else’s delay uses float, even though no time is due yet.
- Report float on the critical and near-critical paths in every schedule update, with the reason for any change.
- Don’t hide float. A clean schedule with visible float is easier to defend than a padded one.
If you are the owner
- State float ownership plainly in the contract.
- Ask for float to be reported with each update, and have the baseline checked for hidden float.
- Treat float as something you can waste. A slow review costs you nothing today and a time extension later.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.