Recovery schedules: Behind schedule? See the real options.

When an update shows the finish date slipping, we find what is driving it, model the ways back, and give you a recovery schedule the team can deliver and the owner can accept.

Typical fee $2,500 – $4,000 See pricing

A wall of electrical meter sockets in an apartment building’s meter room

The short answer

What is a recovery schedule?

A recovery schedule shows how a project that has fallen behind will regain its contract dates — or get as close as is realistic — by resequencing work, adding crews or shifts, overlapping activities or re-phasing turnover. Many contracts require one once the projected completion slips past a set threshold.

The risk with recovery schedules is wishful thinking: durations shortened on paper with no plan behind them. A credible one starts from an honest diagnosis, tests each option against crew sizes, access and inspections, and states plainly what each recovery measure requires.

What’s included

What the work covers.

Diagnosis

We trace the slip to the activities and events that caused it, using the updates and the project record.

Resequencing options

Changes in work flow — by floor, area or trade — that gain time without adding cost, tested for trade stacking and access.

Added-resource options

Extra crews, extended shifts or weekend work, modeled on the critical and near-critical paths, where they will actually move the date.

Procurement and temporary measures

Alternates, expediting, partial deliveries and temporary systems that take a late item off the critical path.

Side-by-side comparison

Each option is shown with the time it recovers, what it takes and what could go wrong, so the decision is an informed one.

Tracking

Recovery activities are flagged in the schedule, so each look-ahead and monthly update can show whether the time is coming back. Those updates are a separate service.

Sample deliverable

The options side by side, trade-offs included.

Recovery options compared

Illustrative example

OptionTime recoveredWhat it takesWatch for
Equipment start-up on temporary power2–3 weeksTemporary service or generator; inspector acceptanceSteps that still need permanent power
Commissioning overlapped with final inspectionsAbout 1 weekA system-by-system sequence agreed with the commissioning agent and the inspectorsNo room to retest a system that fails
Saturday shifts to set and terminate the gearA few daysPremium time for the electrical crewCrew fatigue; inspections on weekdays only
Phased turnover by floorEarlier use of lower floorsOwner and building-official agreementLife-safety systems must be complete

How it works

From first call to delivery.

  1. Check the current schedule

    We confirm the latest update is sound, so the recovery is built on a true starting point. If it needs repair first, we quote that before going further.

  2. Find the drivers

    Critical and near-critical paths are traced to the specific activities holding the date.

  3. Work the options

    A session with your project manager, superintendent and key trades generates realistic measures.

  4. Model and compare

    Each option is built into the schedule and its effect on completion is measured.

  5. Issue and track

    You receive the recovery schedule and narrative. Progress against it is then tracked in your monthly updates or look-aheads.

Deliverables

What you receive

  • Recovery schedule in native format (.xer or .mpp)
  • Narrative describing causes, measures and assumptions
  • Options comparison with time recovered by measure
  • Before-and-after critical path layouts
  • Tracking view for recovery activities

To get started

What we need from you

  • The current schedule update and the baseline
  • The cause of the slippage as the team understands it
  • Subcontractor capacity for added crews or shifts
  • Status of procurement and outstanding approvals
  • Any owner correspondence requesting recovery

Common questions

Questions, answered.

How much does a recovery schedule cost?

Typically $2,500 to $4,000, depending on the condition of the current schedule and the number of options to model. You receive a fixed quote first. The fee covers building and comparing the options and issuing the recovery schedule, with two rounds of the owner’s comments. Tracking the recovery afterward is done in the monthly update or look-ahead, which is a separate service, and a current update that needs repair before it can be used is quoted first. See our pricing page.

What is the difference between recovery and acceleration?

Recovery is the contractor making up time it is responsible for, generally at its own cost. Acceleration is finishing earlier than the contract, as properly extended, requires — usually at the owner’s direction, or because a time extension that was owed was not granted. The schedules can look alike; who pays depends on the contract and on who caused the delay.

Can every late project be recovered?

No. Sometimes the honest answer is a revised completion date with the reasons behind it. We show what is achievable, what it takes, and where the remaining exposure sits.

Will the owner accept our recovery schedule?

Acceptance depends on your contract and the reviewer, so we can’t promise it. A specific recovery schedule gives the reviewer far less to object to. We show the measures as real activities with logic and resources behind them, not as shortened durations, and explain each one in the narrative.

We didn’t cause the delay. Do we still need a recovery schedule?

Check your contract and its notice requirements first. Where a delay is someone else’s responsibility, the usual route is a time impact analysis and a request for a time extension. We can prepare both, and keep the record clear about which days are being recovered and which are being claimed.

Free 30-minute consultation

Bring your schedule, your spec or just your questions.

Thirty minutes with a scheduler, no obligation. We will look at where your project stands and tell you plainly what would help.

Call Free consultation