Data date Nov 1, 2026 Progress through Oct 31
Projected completion Jun 4, 2027 Contract: May 14, 2027
Change this period +21 days Calendar days. On time last month
Critical path Switchgear Was interior finishes
What changed this period
Framing topped out on level 5 and roofing started on the east half. The switchgear manufacturer revised its ship date by ten weeks, to February 19, 2027.
What is driving completion
Switchgear delivery now controls permanent power, elevator inspection, commissioning and turnover. Interior finishes, critical last month, now have three weeks of float against the projected date, and none against the contract date.
Decisions needed
- Authorize temporary power for equipment start-up — needed by November 13, 2026.
- Release the elevator installer to mobilize on temporary power.
- Confirm whether phased turnover by floor is acceptable to the owner.