A notice of delay is a written statement, usually from contractor to owner, that an event has happened and may delay completion. It must be given within the contract’s notice period, which is usually short. AIA A201-2017 allows 21 days to initiate a claim. FAR 52.249-10 allows 10 days from the start of the delay.
A notice does not have to prove the delay or count the days. That is the job of the analysis that follows. The notice has to say what happened, and say it in time.
Key points
- A notice says time may be affected, and the analysis that follows shows by how much.
- Give notice when the event is known, not when its full effect is.
- Name the affected activities by ID, and say whether they are critical in the latest update.
- Late notice can cost an otherwise sound request, so read the notice clause before you need it.
What a notice of delay is, and what it is not
A notice of delay puts an event on record while the owner can still act on it: inspect the condition, change a decision or direct the contractor. It is the first and shortest of four documents that are often confused.
| Document | What it says | When it is sent |
|---|---|---|
| Notice of delay | An event has happened and time may be affected | Within the contract’s notice period, when the event is known |
| Change order request | The price, the time or both should change, with the pricing behind it | When the change can be priced |
| Time impact analysis | How many days the event moves the completion date | With the notice or after it, once the event can be modeled |
| Claim | A formal demand for time, money or both under the contract | As the claims clause provides |
On some standard forms, giving notice is the step that starts a claim, so read the notice and claims clauses together.
When notice has to be given
The contract sets the deadline. Three examples:
- AIA A201-2017 section 15.1.3.1. A claim is initiated by notice, within 21 days of the event or of first recognizing it, whichever is later.
- AIA A201-2017 section 3.7.4. Notice of concealed or unknown site conditions is due before they are disturbed, and no later than 14 days after first observing them.
- FAR 52.249-10. In federal fixed-price construction contracts, written notice is due within 10 days of the start of the delay, unless the Contracting Officer extends the period.
Your contract may set a different limit, and some owners allow only a few days. Check your contract for the number of days, what starts the clock, who must receive the notice and how it must be delivered.
Give notice when the event is known, not when its full effect is. Each clock above starts with the event, with first recognizing or observing it, or with the start of the delay. None waits for the days to be counted.
Late notice can cost an otherwise sound request. By then the owner has lost the chance to act, and some contracts say outright that a request without timely notice is waived. How strictly a clause is enforced depends on the contract and the governing law.
None of this is legal advice. Have counsel review any notice in a dispute, and do not let the review carry it past the deadline.
What to put in a notice of delay
One page of facts is enough. If your contract lists what a notice must contain, follow that list. Otherwise include seven things.
- The event and its date. What happened, where, and the date it began or was first recognized. Say whether it is still going on.
- The clause. The contract provision the notice is given under.
- The activities affected. Named as the schedule names them, with the activity ID where possible, so a reviewer can find them.
- Critical or not. Whether that work is on the critical path in the latest schedule update. If it has float, say how much.
- The expected effect. An estimate in days, labeled as an estimate, or a statement that the analysis will follow. Some contracts require an estimate, so check your contract.
- Mitigation. What is being done to limit the delay: crews moved, work resequenced, alternates priced.
- What you need, and by when. The decision, drawing, access or direction required from the owner, and the date it is needed.
If you never open the scheduling software, ask your scheduler for the activity IDs, their float and the data date (the cutoff date) of the latest update.
A sample notice of delay
The example below is illustrative, with made-up details. It assumes general conditions based on AIA A201-2017, so it cites section 3.7.4. Use the clause, addressees and delivery method your own contract requires.
Notice of delay: utility line at the east footings
To the Owner and the Architect. April 14.
Event. On April 13 the Contractor uncovered a utility line in the east footing excavation. It is not shown on the Contract Documents and has not been disturbed. Work there has stopped. Notice is given under Section 3.7.4 of the General Conditions.
Activities affected. A1040, Form and pour east footings, and A1050, East foundation walls. Both are on the critical path in Schedule Update 04 (data date March 31).
Effect. Completion may be delayed. The effect is not yet known, and a time impact analysis will follow.
Mitigation. The crew has moved to the west footings.
Decision needed. Direction by April 20: relocate, protect or abandon the line.
That is the whole notice, sent the day after the event. It does not claim a number of days it cannot yet support.
How the schedule backs it up
A notice is only as good as the records behind it.
- The latest update. It shows what was planned, and what was critical, before the event. That is why the notice names it.
- Daily reports. From the first day, record what stopped, where the crew went and what stood idle. For a weather delay, keep the records listed in our guide to weather days.
- The next update. It records the affected activities as they actually stand, and its narrative lists the event, the notice and the date it was given. Our schedule narrative example shows where.
- The time impact analysis. The event is modeled as a fragnet, a small group of linked activities, in the last accepted update with a data date before the event began. Our time impact analysis guide works through the steps.
If the affected work has float, the analysis may show no delay to completion. The notice still records whose event used the float. Our guide to who owns the float explains why that matters.
What happens after notice is given
- Acknowledgment. The owner or its representative confirms receipt in writing, notes the date received and answers the question asked. A reply can confirm receipt without agreeing that time is due.
- The analysis. The contractor measures the effect and submits it in the form the contract requires. Some specifications set a deadline for this too.
- Negotiation. The days are negotiated with the price and, where possible, settled in the same change order. If the price is agreed first, the change order should say that time is still open.
- Updated notice. If the event is ongoing, keep reporting it in each update. Some contracts also require updated notices or analyses at set intervals, and others need only one notice. Check your contract.
Owners’ representatives should check each notice against the update: is the activity there, and is it critical? Our guide to reading a schedule update lists what to look for.
Common mistakes
- Waiting for the number. The clock usually starts with the event, not with the count of days.
- Saying it, or sending it the wrong way. A remark in the weekly meeting is not written notice. Under some contracts, neither is an email.
- Being vague. “The design is delaying us” gives no event, no date and no activity.
- Calling work critical when the update shows float. The owner’s reviewer will open the file.
- Holding back to keep the peace. A notice is a contract step, not an accusation.
- Sitting on a subcontractor’s notice. Your own deadline keeps running while it waits.
- No follow-through. A notice with no analysis behind it is easy to set aside.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.