Weather Days in a Construction Schedule: Baseline to Time Extension

How to plan for normal weather in a baseline schedule, record weather days during the job, and show when unusually severe weather supports a time extension.

In this guide

Weather days are handled in two parts. The contractor is expected to plan for normal weather, so the baseline schedule includes it, as non-work days in a weather calendar or as a named allowance activity. Unusually severe weather may support a time extension if the contract allows it and the critical path was delayed.

The contract decides where normal ends and unusually severe begins. The schedule’s job is to make the allowance visible and, during the job, to show what the weather did to the work.

Key points

  • Normal weather is the contractor’s to plan for, and the baseline should show how.
  • Put the allowance in a weather calendar or a named activity, not inside activity durations.
  • Only weather beyond the anticipated days, on critical work, is likely to earn time.
  • Write up weather the day it happens, and give notice within the contract’s time limit.

Normal weather or unusually severe weather?

Most sites lose days to rain, cold, wind or heat in an ordinary year. Contracts generally treat that normal (anticipated) weather as something the contractor should have expected when it agreed to the completion date. The contract time is taken to include it, so it earns no extension.

Unusually severe weather is weather worse than could reasonably have been expected for that place and time of year. A week of rain in the wettest month may be normal. The same week in the driest month may not be.

Many contracts treat unusually severe weather as an excusable delay: more time, but usually no more money. FAR 52.249-10, used in federal fixed-price construction contracts, lists it among the causes that can excuse a delay.

Contracts draw the line in different ways. Some list the weather days to expect each month. Some set a rainfall or temperature threshold. Some say nothing. Check your contract before the baseline is built.

Three ways to put normal weather in the baseline

Normal weather gets into a baseline schedule in one of three ways. Only the first two can be checked.

  • Non-work days in a weather calendar. Weather-sensitive activities get their own calendar, with each month’s expected weather days marked as non-work days. Work in a wet month then takes longer than the same work in a dry one. If a delay pushes it into a worse season, the dates adjust by themselves.
  • A weather allowance (contingency) activity. One named activity near the end of the critical path holds the expected days for the whole job. Each time weather stops critical work for a day, its remaining duration is cut by a day, so completion holds until the allowance is used up. It is easy to read, but it treats every season alike.
  • Padded durations. A few days are added to each exterior activity. Nobody can see how many were allowed or how many are left, and a reviewer cannot tell the allowance from hidden float.

Use the method your specification names. If it names none, use one of the first two, and state the days and their source in the baseline narrative.

Which activities are weather-sensitive?

Primavera P6 and Microsoft Project both let each activity follow its own calendar. The weather calendar belongs only on work the weather can stop.

Type of workCalendarWhat usually stops it
Earthwork, excavation and underground utilitiesWeatherRain, saturated or frozen ground
Exterior concrete, masonry and pavingWeatherRain, temperatures outside the specified limits
Steel erection and other crane workWeatherHigh wind, lightning
Roofing, waterproofing and exterior finishesWeatherRain, wind, wet or cold surfaces
Interior work after dry-inStandardVery little, once the building is enclosed
Submittals, procurement and off-site fabricationStandardNot affected by site weather

Different weather stops different work, so larger jobs sometimes carry more than one weather calendar. And the exposure shrinks: once the building is dried in, interior work no longer depends on the weather.

Where the expected number of days comes from

Start with the contract. If it has a table of anticipated weather days by month, use those numbers: any later request will be measured against them.

If it gives no numbers, build the allowance from historical records for the weather station nearest the site. NOAA’s climate normals are one source: long-term monthly averages for individual stations, including the average number of days that reach set amounts of precipitation or fall below freezing.

  1. Decide what counts as a lost day for the work: how much rain, how cold, how windy.
  2. Count the average number of those days in each month.
  3. Adjust for the work week. The records count calendar days, and some fall on weekends.
  4. State the station, the years of record and the rule you applied in the baseline narrative.

An allowance with a stated source can be checked. A round number cannot.

Recording weather during the job

A weather request stands or falls on the daily reports, because what matters is what the weather did to the work. On every day weather affects the site, the superintendent’s report should record:

  • The conditions. Rain, snow, wind or temperature, and roughly when it started and stopped.
  • What was planned. The work on the look-ahead for that day, and whether it was on the critical path.
  • What could not be done. Which activities stopped, for all or part of the day, and which crews and equipment stood by or went home.
  • Drying-out days. Days after the weather has passed when the ground is still too wet to work. Record them, whether or not your contract counts them.

Keep the official record from the nearest weather station for the same dates. In each monthly schedule update, report the weather days expected, the days lost and the running total, even when no extension is due.

When weather supports a time extension

The contract governs, and this is not legal advice. In general, a request for time has to show four things.

  1. The weather was worse than anticipated. Actual weather days exceeded the anticipated days for that month. Only the excess counts. AIA A201-2017 section 15.1.6.2 asks for data showing the weather was abnormal for the period, could not reasonably have been anticipated and had an adverse effect on the scheduled construction.
  2. It stopped planned work. The daily reports show weather-sensitive work was scheduled and could not proceed.
  3. The work was on the critical path. Weather that delays work with float uses up the float and usually earns no time.
  4. Notice was given in time. FAR 52.249-10 requires written notice within 10 days of the start of the delay. AIA A201-2017 section 15.1.3.1 requires a claim to be initiated by notice within 21 days of the event or of first recognizing it. Your contract may set a different limit.

An example, with made-up numbers. The contract anticipates five weather days in April. Rain stops the footings, which are critical, on nine working days. The baseline already allowed for five. The other four push completion, so the request is for four days, not nine.

If weather is stopping critical work, do not wait for the month-end count to give notice. Show the effect with a time impact analysis or, where the contract allows, with the schedule update for that period. If the request is disputed, consult counsel.

Common mistakes

  • No weather in the baseline. A schedule that assumes good weather every working day shows a finish date the weather won’t support.
  • Weather buried in durations. The allowance cannot be seen or tracked.
  • The weather calendar on everything. Interior work and procurement do not stop for rain.
  • Counting every wet day. Weekends, days with no weather-sensitive work planned, and days that only touched work with float generally do not support a request.
  • Reading float across calendars. Activities on different calendars can show different float on the same chain of work. Identify the critical path by the longest path.
  • Thin daily reports. An entry that says “rain” and nothing about what was planned or what stopped.
  • Late notice. Raising the weather at the end of the job can cost the entitlement.

This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.

Quick answers

Questions, answered.

What is a weather day?

A day on which weather prevents work on the controlling activity: the work that will delay completion if it is delayed. Rain on a day when only interior work was planned is generally not one. Contracts define the term in different ways, so check yours.

How many weather days should a construction schedule include?

There is no standard number. It depends on the site, the season, the type of work and the contract. Use the contract’s table if it has one. Otherwise build the allowance from historical records for the nearest weather station and state the source.

Does the contractor get paid for a weather delay?

Usually not. Most contracts treat unusually severe weather as excusable but not compensable: the contractor gets more time and no added payment. The contract governs, so read the clause, and consult counsel if the point is disputed.

Can unused weather days be carried into a later month?

Only if the contract says so. Some contracts compare each month on its own. Others keep a running total for the whole job, so a dry month can offset a wet one.