Free schedule narrative template for Word: A monthly narrative with the outline already written.

A free Word document for the narrative that goes with each monthly schedule update. It has the ten headings from our guide, a one-line instruction under each and a worked example to write over, and there is no form to fill out.

Word document (.docx) · 7 KB · No sign-up · No macros

The first page of the schedule narrative template: the title, a table of project details to fill in, a box on how to use the template, and the first four numbered headings, each with an instruction line and an example
The first page of the template, with its worked examples to write over. The project they describe is made up for illustration.

What is inside

Six things already on the page.

The ten headings from the guide

From project, update number and data date through to attachments, in the order of the outline in our guide. They are numbered, and each is set in the built-in Heading 2 style, not just in bold.

One instruction under each heading

A gray line that says what belongs there: what started, what finished and what fell short of the plan, for example.

A worked example in every section

The same illustrative project as the guide: a five-story mixed-use building at Update 08, the month its switchgear delivery slips. Each example begins with the word “Example,” so it is easy to find and delete.

Three tables, already drawn

Changes this period, with the reason for each. Milestone status, with contract date, previous forecast, current forecast and variance. Decisions needed, with from whom and by when.

A details block at the top

Project, update number, data date, period covered, prepared by and date issued.

Laid out to print

US Letter with 1-inch margins, Arial throughout, and “Page X of Y” at the foot of every page.

Free download

Schedule narrative template

Free to use and to adapt on your own projects.

Download the template

Word document (.docx) · 7 KB · No sign-up

How to use it

From the download to an issued narrative, in six steps.

  1. Fill in the details

    Project, update number, data date, period covered, who prepared it and the date issued.

  2. Write under each heading

    Write your own text, then delete the gray instruction line and the example.

  3. Type over the tables

    Replace the example rows and add rows as you need them.

  4. Keep the headings

    Use the same headings every month, and keep it short: two to four pages is usual.

  5. Check your specification

    Add anything your contract’s scheduling specification requires.

  6. Issue it

    Delete the how-to box, then send the narrative with the native schedule file.

Beyond the template

When the headings are the easy part.

A template gives you the headings. It cannot tell you why the completion date moved, which path is now critical or what was changed in the schedule since last month. Those answers have to come out of the schedule itself, every period.

That is the part we do. Each month we status the schedule from a short call with your superintendent or project manager, recalculate it, compare it with the baseline and the last update, and write the narrative, ready to submit with the native file.

How our schedule update service works

Common questions

Questions, answered.

Is the schedule narrative template really free?

Yes. There is no form, no email address and no trial period. Download it, use it on your own projects and change it to suit them.

Does the narrative template use macros?

No. It is a plain .docx document: text, headings and a few small tables. There are no macros and no images. Word may ask you to click Enable Editing first, as it does with any downloaded file.

Will it work in Google Docs or Pages?

It is a standard Word document (.docx). We have not tested it in Google Docs or Pages, so we can’t promise the tables and the numbered headings look the same there.

Do I have to keep all ten headings?

They follow the outline in our guide, and the guide’s advice is to keep the same headings every month, so readers learn where to look. If a section has nothing to report, say so in a line rather than deleting it. Where your contract’s scheduling specification asks for something different, follow the specification. The template is general information, not legal advice.

Can I use it for a baseline schedule narrative?

It is laid out for monthly updates. A baseline narrative, often called the basis of schedule, records how the plan was put together: calendars, durations, sequence, the critical path and more. It needs different headings, and our guide lists them.