Free schedule narrative template for Word: A monthly narrative with the outline already written.
A free Word document for the narrative that goes with each monthly schedule update. It has the ten headings from our guide, a one-line instruction under each and a worked example to write over, and there is no form to fill out.

What is inside
Six things already on the page.
The ten headings from the guide
From project, update number and data date through to attachments, in the order of the outline in our guide. They are numbered, and each is set in the built-in Heading 2 style, not just in bold.
One instruction under each heading
A gray line that says what belongs there: what started, what finished and what fell short of the plan, for example.
A worked example in every section
The same illustrative project as the guide: a five-story mixed-use building at Update 08, the month its switchgear delivery slips. Each example begins with the word “Example,” so it is easy to find and delete.
Three tables, already drawn
Changes this period, with the reason for each. Milestone status, with contract date, previous forecast, current forecast and variance. Decisions needed, with from whom and by when.
A details block at the top
Project, update number, data date, period covered, prepared by and date issued.
Laid out to print
US Letter with 1-inch margins, Arial throughout, and “Page X of Y” at the foot of every page.
Free download
Schedule narrative template
Free to use and to adapt on your own projects.
How to use it
From the download to an issued narrative, in six steps.
Fill in the details
Project, update number, data date, period covered, who prepared it and the date issued.
Write under each heading
Write your own text, then delete the gray instruction line and the example.
Type over the tables
Replace the example rows and add rows as you need them.
Keep the headings
Use the same headings every month, and keep it short: two to four pages is usual.
Check your specification
Add anything your contract’s scheduling specification requires.
Issue it
Delete the how-to box, then send the narrative with the native schedule file.
Beyond the template
When the headings are the easy part.
A template gives you the headings. It cannot tell you why the completion date moved, which path is now critical or what was changed in the schedule since last month. Those answers have to come out of the schedule itself, every period.
That is the part we do. Each month we status the schedule from a short call with your superintendent or project manager, recalculate it, compare it with the baseline and the last update, and write the narrative, ready to submit with the native file.
Common questions
Questions, answered.
Is the schedule narrative template really free?
Yes. There is no form, no email address and no trial period. Download it, use it on your own projects and change it to suit them.
Does the narrative template use macros?
No. It is a plain .docx document: text, headings and a few small tables. There are no macros and no images. Word may ask you to click Enable Editing first, as it does with any downloaded file.
Will it work in Google Docs or Pages?
It is a standard Word document (.docx). We have not tested it in Google Docs or Pages, so we can’t promise the tables and the numbered headings look the same there.
Do I have to keep all ten headings?
They follow the outline in our guide, and the guide’s advice is to keep the same headings every month, so readers learn where to look. If a section has nothing to report, say so in a line rather than deleting it. Where your contract’s scheduling specification asks for something different, follow the specification. The template is general information, not legal advice.
Can I use it for a baseline schedule narrative?
It is laid out for monthly updates. A baseline narrative, often called the basis of schedule, records how the plan was put together: calendars, durations, sequence, the critical path and more. It needs different headings, and our guide lists them.
Keep reading
Guides that go with it
The schedule narrative: example and outline
What a construction schedule narrative is, what owners expect at baseline and at each monthly update, a full written example, and a reusable outline.
How to read a schedule update
A guide for owners and project managers: eight questions that show whether a monthly schedule update is telling the truth about progress and the finish.
Notice of delay: what to send and when
What a notice of delay in construction is, when it has to be given, what to put in it, a short sample, and how the schedule supports it.
How we can help
Related services
Schedule updates & reporting
Your schedule statused against real progress every period, with a plain-English report on what changed and what it affects.
CPM baseline schedules
A complete, logic-driven plan of record, built with your team and checked against the specification before it is submitted.
Owner-side schedule review
An independent check of your contractor’s baseline and monthly updates, with written comments and a clear read on the finish date.