A cost-loaded schedule is a CPM schedule in which every activity carries a share of the contract price. Add up the activity costs by month and you have a cash-flow forecast. Multiply each one by its measured percent complete and you have the value of work in place.
That second use is why owners ask for it. A cost-loaded schedule ties the pay application to measured progress on the schedule, so the two can no longer tell different stories.
Key points
- Cost loading assigns the contract value to schedule activities, and the total must equal the contract price.
- It produces a cash-flow curve and gives pay applications an objective basis.
- Build it from the schedule of values, and avoid front-end loading.
- It adds work to every update. If nobody requires it, a simpler cash-flow curve may do.
How a cost-loaded schedule works
Each activity is given a budgeted cost: the portion of the contract price that the work represents. The schedule software spreads that cost across the activity’s duration. Summed by month, the result is a forecast of how much work will be put in place, and billed, in each period.
Because every activity has both an early and a late date, the software can produce two curves: spending if everything starts as early as it can, and spending if everything starts as late as it can. Realistic progress should fall between the two. A planned billing curve that sits above the early curve is asking to be paid ahead of the work.
Who requires one
- Public owners. Many require a cost for every activity. The City of Los Angeles Bureau of Engineering’s schedule specifications, for example, call for the cost of each activity to be listed, with the total equal to the contract value.
- Lenders and developers, who use the cash-flow curve to plan draws.
- Large private owners, who want payment tied to schedule progress.
The requirement is usually in the scheduling specification, alongside the software and the update cycle. Read it before pricing the schedule: cost loading changes how the schedule has to be structured.
How to build one
- Start from the schedule of values. The cost-loaded schedule and the schedule of values must agree, so build one from the other.
- Map values to activities. A single line such as “Level 3 framing” may be split across several activities by area. Keep the split traceable.
- Put cost on work, not on milestones. Milestones have no duration to earn against.
- Handle procurement deliberately. Decide, in line with the contract, whether fabrication and stored materials carry cost or whether all of it sits on installation.
- Spread general conditions across the project’s duration on a level-of-effort activity.
- Reconcile. The total of all activity costs must equal the contract price, to the dollar.
- Check the curve. Run the early and late cash-flow curves and look for anything that billing patterns alone would not explain.
Using it for pay applications
Each month, the schedule is updated with actual progress. Percent complete multiplied by budgeted cost gives the value of work installed on each activity, and the total is the amount of work in place. Scheduling software reports a similar figure as earned value, but calculates it by whichever earning rule the file is set to, so the two agree only when that rule measures installed work. The percentage has to be a measure of work installed, such as quantities or agreed steps, not the share of the duration used up. That figure is compared with the pay application.
The two will not match to the dollar: stored materials, retainage, cutoff dates and changes still awaiting approval all sit between them. A difference those items do not explain is worth running down before the invoice is paid. Approved change orders enter the schedule as new activities with their own cost, so the total keeps matching the revised contract price.
Common mistakes
- Front-end loading. Putting too much cost on early activities so more is billed up front. Owners watch for it, and it sours the review.
- A few activities carrying most of the money. If 60% of the value sits on ten activities, percent complete becomes a negotiation.
- Long activities with large costs. Progress on a 60-day activity is a judgment call. Shorter activities can be measured.
- A total that doesn’t tie. A schedule that adds up to slightly more or less than the contract will be rejected.
- Forgetting the upkeep. Every change order and every resequencing has to be carried through the cost loading. Budget time for it in each update.
Cost loading and resource loading
They are related but different. Cost loading assigns dollars. Resource loading assigns labor, equipment or quantities, which lets the schedule show crew sizes over time and reveal weeks where a trade is overstretched. Some specifications ask for one, some for both.
Do you need one?
If the contract requires it, yes. If not, weigh the benefit against the upkeep. For a lender’s draw schedule or a developer’s pro forma, a cash-flow curve built directly from the schedule of values and the main schedule milestones is often enough, at a fraction of the effort.
We build both as part of preconstruction and baseline scheduling, and will tell you plainly which one your situation calls for.
This guide is general information about construction scheduling, not legal or contract advice. Your contract governs.